maths · General Studies II (CSAT)

3 men or 7 women finish a work in 32 days. 7 men and 5 women together will finish the twice of this work in

Hinglish: 3 admi ya 7 aurten ek karya ko 32 din mein pura kar lete hain. 7 admi aur 5 aurten milkar uske dugune karya ko pura karenge

Answer and explanation

Answer: B. 21 days

3M = 7W, so 1M = 7/3 W. Work = 7 × 32 = 224 woman-days. 7M + 5W = 49/3 + 5 = 64/3 W. Time for double work = 448 ÷ (64/3) = 21 days.

Asked in UPPSC CSAT 2020

This is a previous year question (PYQ) of UPPSC CSAT. यह प्रश्न UPPSC CSAT 2020 में पूछा गया था।