480 persons working 10 hours per day complete one-fourth of a work in 10 days. How many additional persons are to be employed in order to complete the remaining work in 20 days, working 8 hours per day?
Related questions
Two persons A and B complete a task in 15 days, when they work together. Person A completes the task in 20 days if he works alone. How many days will B take to finish the task alone?
Time & WorkIf 4 men or 6 women can do a piece of work in 12 days working 7 hours a day. How many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day?
Time & Work12 men working 8 hours a day can completely build a wall of length 100 m, breadth 20 cm and height 5 m in 10 days. How many days will 16 men working 10 hours a day require to build a wall of length 2…
Time & WorkA group of workers can complete a job in 12 days. If they are joined by 4 more workers, they can complete the job in 8 days. How many workers were there originally?
Time & WorkMohan can do a bit of work in 25 days which can be completed by Sohan in 20 days. Both together labour for 5 days and afterward Mohan leaves off. How long will Sohan take to complete the remaining wo…
Time & Work