A can complete a particular task in 25 days whereas B can finish that task in 15 days. A and B together do the work for 5 days and then A leaves the task. How many days will B take to complete the remaining task?
Related questions
Two persons A and B complete a task in 15 days, when they work together. Person A completes the task in 20 days if he works alone. How many days will B take to finish the task alone?
Time & WorkMohan can do a bit of work in 25 days which can be completed by Sohan in 20 days. Both together labour for 5 days and afterward Mohan leaves off. How long will Sohan take to complete the remaining wo…
Time & WorkA can do a piece of work in 30 days and B in 20 days. They work together for 4 days and B leaves. A will finish remaining work in
Time & WorkA does 80% of a work in 20 days. He then calls in B and they together finish the remaining work in 3 days. How long B alone would take to do the whole work?
Time & Work10 women can complete a work in 7 days and 10 children take 14 days to complete the work. How many days will 5 women and 10 children take to complete the work?
Time & Work