Answer: D. C, B, E, A, D

HIRAKUD (Mahanadi, Odisha) – inaugurated by Nehru in 1957, the first major multipurpose project of independent India to be completed. BHAKRA (Sutlej, HP) – completed in 1963 (Nehru dedicated it to the nation on 22 October 1963, calling such dams 'temples of resurgent India'). NAGARJUNA SAGAR (Krishna) – foundation 1955, water released to canals in 1967. TEHRI (Bhagirathi, Uttarakhand) – after decades of protest (Sunderlal Bahuguna), stage-I power from 2006. SARDAR SAROVAR (Narmada, Gujarat) – raised to its full height of 138.68 m and dedicated to the nation on 17 September 2017, after the long Narmada Bachao Andolan (Medha Patkar, Baba Amte) over displacement. So C, B, E, A, D. Option B puts Bhakra before Hirakud (construction began at Bhakra in 1948, but Hirakud was finished first). These dams are linked to the syllabus items 'irrigation and multipurpose projects' and the old syllabus item 'multipurpose schemes'. Type: Predicted question Source: Mixed revision: multipurpose projects (chronology pattern of UGC NET December 2025 Q54 and Q69)

Asked in UP PGT Geography Topic Test 7 - Geography of India: Mixed Test 1 (whole Geography of India syllabus) (2081)

This is a previous year question (PYQ) of UP PGT. यह प्रश्न UP PGT Geography Topic Test 7 - Geography of India: Mixed Test 1 (whole Geography of India syllabus) में पूछा गया था।

Related questions